Baseball Field Project
The Baseball Field Project began on February 25, 2008. A temporary pathway has been identified for pedestrians to use between the main campus and Q Bldg. during the 3-4 month project.
Baseball Field Schedule 7/8/08:
Complete Irrigation Laterals
Complete Curbs and sidewalks (98%)
Complete chain link (98%)
Install roofing (1 week)
Final grade for grass and D/G
Install ballfield DG , Infield mix Sod and Stolins ( stolins expected appx 7-11)
Install flagpole
Power to Irrigation controller
Install dugout doors
|