The upcoming Q Building Pathway Project began February 25, 2008. A temporary pathway has been identified for pedestrians to use between the main campus and Q Bldg. during the 3-4 month project.
Q Pathway Schedule 7/8/08:
Electrical at sidewalks (begin wire installation)
Low voltage underground (waiting for back ordered 15 degree bends- any day)
Start retaining wall @ fitness center- material onsite
Sidewalk installations at Library (95% complete- waiting for Chiller/Data project completion in joint area)
Complete subgrade for remaining sidewalks
Complete handrail installation
Begin irrigation systems
March 19, 2008 Q Building HVAC Mechanical Renovation
This project will replace the aging HVAC and Energy Management System equipment components for the occupied areas of the Maricopa County Library and Arizona Agribusiness and Equine Center Charter School within the next several months. Of the building’s total footprint (65,929 sq. ft.), the air-conditioning upgrades will affect approximately 20,642 square feet.